Timelines for a design-build project vary based on complexity, home size, level of detail, material sourcing, and design elements—such as the intricate connections in our modern homes with extensive floor-to-ceiling windows and wider spans, which require precise tolerances and can extend durations.

Assuming you already own the land, the full process from initial design to move-in typically spans 16 to 24 months. This breaks down as follows: plan design takes 4 to 8 months, permitting 1 to 2 months, and construction 10 to 12 months for homes under 6,000 square feet or around 14 months for those 6,000 square feet and larger.

We recommend involving us early through a pre-construction agreement, even during land acquisition, to provide expert guidance and help avoid costly mistakes. We leverage advanced technology for real-time updates on all aspects of the project and secure your project slot once plans are approved.