The short answer

Most Artistic Contractors homes take about 12 to 18 months from groundbreaking to completion, depending on size and complexity. That range covers construction only. Land analysis, design, engineering, pricing and permitting come first, and how long they take depends mostly on the design and on how quickly decisions are made. We plan that part with each client rather than quoting one number.

The phases at a glance

Each phase produces something specific, needs certain decisions from you, and depends on the one before it.

Phase What it produces Decisions needed from you Depends on
1. Land analysis A read on setbacks, slope, drainage, trees, utilities, built-upon area and views Whether the lot suits the house you want; what matters most on the site The lot, a survey and the recorded plat
2. Design, or review of your architect’s plans A floor plan and elevations you approve; with design-build, a 3D model you can walk through Program, room sizes, style, major windows, structure-changing choices Land analysis, so the plan fits the site
3. Engineering Structural, site and any stormwater or septic design Few, if the design is settled; layout changes here send drawings back Approved design
4. Budget and Fixed Final Price Written scope, priced from the plans, with allowances for finishes Allowance levels; early selections such as cabinetry Engineered plans
5. Permitting Approved plans and issued permits Answers to reviewer comments when they affect the design Complete engineered plans; inside Charlotte, City lot review before the County building permit
6. Construction The house, inspected in stages Remaining selections on schedule; any changes in writing Permits, price and a ready site

What has to be in place before groundbreaking

  • Engineered plans that match what you approved
  • Written scope and allowances, and the Fixed Final Price, which is set once engineered plans, scope and allowances are complete
  • Building permit issued; inside the City of Charlotte, the City’s Individual Residential Lot review is approved before the County permit (how permitting works)
  • Related approvals where they apply: septic, well, pool, site or floodplain permits, and a Certificate of Appropriateness in a local historic district
  • Long-lead items identified and, where it helps the schedule, ordered
  • Site access, erosion control and staging planned

Before groundbreaking: phase by phase

Land analysis

We look at the lot first: size, topography, drainage, sun, stormwater, views, trees, setbacks, buffers, utilities and the built-upon area the lot is allowed. Problems found here are inexpensive to solve; problems found during construction are not. See building on your lot in Charlotte.

Design, or review of your architect’s plans

If we design the home, our in-house team develops it through design-build, with 3D design so you can walk through rooms and views before approving the plans. If you have an architect, we review the drawings for buildability and cost and coordinate engineering as part of building from your architect’s plans.

The pace of this phase is set mostly by decisions. A clear program and prompt approvals keep it moving; late changes to layout or structure send drawings back through engineering.

Budget and the Fixed Final Price

We build a detailed budget and written scope from the plans, using digital takeoffs to measure the drawings and price the home as designed. Core scopes such as foundation, framing, structure and HVAC are priced and locked before the build begins, and finish allowances are calibrated to your preferences. Starting cabinetry and other complex selections before groundbreaking improves pricing clarity and keeps those decisions off the critical path.

Permitting

We prepare and submit permit documents and coordinate related approvals. Review times are set by each jurisdiction and change with workload and with the project, so we track them for each home rather than assume a number. Mecklenburg County, for example, publishes an average review goal for house plans after a submittal is accepted; that is one step’s goal, not a permit timeline.

Have a move-in date in mind?

Tell us about the lot and the house. We will lay out a realistic sequence and tell you which decisions will set the pace.

Plan Your Timeline With Us →

During construction

Once plans, price and permits are in place, construction follows a familiar sequence. Each stage is inspected before the next begins.

Stage What happens What you decide around it
Site preparation Clearing, erosion control, access and staging, utility planning Trees to protect, if not already settled
Foundation Footings, foundation walls or slab, waterproofing Nothing new if the plans are final
Framing, roof and windows Structure, roof and openings to a weather-tight shell Exterior selections should already be made
Rough-ins Mechanical, electrical and plumbing, inspected before walls close Lighting, audio-visual and outlet locations
Insulation and drywall Envelope and walls closed Interior paint and trim direction
Interior finishes Cabinetry, trim, tile, flooring, counters, fixtures, paint Remaining finish selections, on schedule
Exterior and site finishes Hardscape, final grading, landscaping Outdoor living details
Completion Final inspections, punch list, handover Walkthrough and warranty orientation

What changes the schedule

Factor Why it matters What helps
Size and complexity Larger homes, complex rooflines, custom millwork and specialty systems take longer to build and finish well It is the main reason the range is 12 to 18 months
The lot Slopes, retaining walls, rock, long utility runs, wells and septic add site work Land analysis before design
Decisions and changes Late selections and changes after construction starts are the most common avoidable delay Settle complex selections before groundbreaking
Weather Extended rain slows site work, foundations and exterior work Sequencing around the season where possible
Lead times Windows, specialty doors, custom cabinetry, imported tile and stone, some appliances Ordering early
Reviews and inspections Timing depends on the jurisdiction Complete submittals and prompt answers to comments

A project example: Tidewater

Upper-level gallery in Tidewater with a wood-plank vaulted ceiling, dark steel beams, clerestory windows and a glass railing
Tidewater, Lake Tillery. Structural steel opens the rear of the house to the lake. Designed by Daron Gaon and built by Artistic Contractors.

At Tidewater on Lake Tillery, Daron Gaon drew the house and modeled it in 3D, geolocated so sun and shadow could be studied on the actual site, before construction drawings were finished. The structural steel that allows the largely glass rear wall was set by crane, so engineering, steel fabrication and crane access all had to be planned ahead of framing. That is the kind of dependency the phase table above is meant to surface early.

How we keep a build on track

  • Land analysis before design, so the plan fits the site
  • A complete, engineered plan set and detailed scope before the Fixed Final Price is set
  • Complex selections started before groundbreaking
  • Active management of trades, materials and inspections
  • Regular updates on progress, selections and milestones; see our process

Frequently asked questions

How long does it take to build a custom home in Charlotte?

Most of our homes take about 12 to 18 months from groundbreaking to completion, depending on size and complexity. Design, engineering, pricing and permitting come first.

Does the 12 to 18 months include design?

No. It covers construction only. Design or plan review, engineering, the budget and permitting happen beforehand.

Why don’t you give a number for design and permitting?

Because it depends on the design, how quickly decisions are made and the jurisdiction’s review. We plan it with each client instead of quoting a figure that may not apply.

What is the most common avoidable delay?

Late decisions and changes after construction starts. Settling selections early, especially cabinetry and other complex items, protects the schedule.

Sources

Start with a realistic sequence

For costs, see our cost guide.

Talk to Us About Your Build →